Building and Trade Permits

At UBC, all new building construction, renovations or building additions need a Building Permit.

Building Permits

UBC administers the BC Building Code for all building and construction activities on campus. This ensures the health, safety, and protection of people and property. All permit applications must comply with the current edition of the BC Building Code.

C+CP Permits and Inspections administers the BC Building Code on campus and issues permits for building and related construction activities.

Technical Safety BC administers electrical and gas trade permits for UBC buildings.

The approval process for a project is based on its scope and whether it is classified as a major or other project.

  • Projects have a construction value greater than $10 million. For these projects, C+CP retains an independent Coordinating Code Consultant (CCC) to perform third party plan review for compliance with the BC Building Code in addition to the internal review done by C+CP. 
  • Projects with a construction value of less than $10 million. For these projects, C+CP reviews all Building Permit applications to ensure they comply with the BC Building Code and issues Building Permits accordingly. 

All Building Permit applications and applicable fees must be submitted to C+CP Permits and Inspections. Fees are payable in accordance with the Schedule of Fees in effect at the time of application, as set out in the Building Permit Application Form and the UBC Development and Building Regulations. 

See Forms and Reference materials for all building permit forms.  

For major projects with a construction value greater than $10 million, submissions must include the following minimum information:

  • A completed Building Permit Application form and UBC Major Projects, Building Permit Application Intake Checklist for Major Projects with an estimate of the contract value. 
  • Documentation listed in the UBC Major Projects, Building Permit Application Intake Checklist
  • A cheque or internal requisition for the amount of the Building Permit Application fee in accordance with Schedule B of these Regulations. Payment of all outstanding fees is required prior to Building Permit issuance. 
  • The required refundable deposit for final design plans to be received as record drawings ($1,000 per drawing to a maximum of $20,000). 
  • In addition to the drawing deposit, a $5,000 refundable deposit is to be held to cover damage to landscape and public realm infrastructure. 

The following process is relevant for Major Projects that have a construction value of $10 million and greater, excluding UBC Renew:

Step 1: Building Permit Application

Based upon certified professional procedures (Architectural Institute of British Columbia & Engineers & Geoscientists of British Columbia) often phased as; 1) excavation & shoring, 2) foundation to grade, and 3) full Building Permit.

  • Confirm documentation received
  • Must conform to approved Development Permit plans
  • Confirm fee payments (BP/IICs/CACs/GVS&DD DCCs; record drawing deposit)
  • Review by Coordinating Code Consultants (CCCs) for compliance with current BC Building Code requirements (collation of assurance schedules and review of documents)
  • Circulate to relevant departments/agencies
  • CCCs identify Code non-compliance issues for applicants to resolve
  • Recommendation from Coordinating Code Consultants to issue permit

Step 2: Chief Building Official Issues Building Permit

  • Notice of other permit requirements (UBC Plumbing and Sprinkler Permits/ Provincial Electrical/Gas/Elevators etc.)

Step 3: Monitoring and Field Reviews

  • CCC and others as required, attend site to verify code compliance
  • Monthly meetings with C&CP/CCCs/UBC Properties Trust (UBCPT)
  • For institutional projects, Project Manager (UBCPT or Project Services) completes survey of below-grade infrastructure, organizes site visit with UBC Utilities for review, and submits “as-built” survey for Infrastructure component

Step 4: Occupancy Permit Application

  • CCC receives and reviews documentation from applicant including:
    • DP compliance checklist
    • Final inspection of Plumbing and Sprinkler Permits
    • Certification of Electrical/Gas/Elevator etc permits

Step 5: Life-Safety Demonstration

  • Onsite coordination of contractors/subcontractors/CCC/Vancouver Fire and Rescue Services to witness operation of life-safety systems (fire detection/suppression, exiting etc)

Step 6: CCC Recommendation for Occupancy

  • Documentation assembled including final letters of assurance from and registered professional of record.
  • Meeting between C&CP and CCC to confirm documentation

Step 7: Chief Building Official Issues Occupancy Permit 

For projects that have a construction value of less than $10 million or projects, submissions must include the following minimum information:

  • A completed Building Permit Application form with an estimate of the contract value and Building Permit Application Checklist for Minor Projects.
  • Documentation as list in the UBC Building Permit Application Checklist for Minor Projects. 
  • A cheque, credit card, or internal requisition for the amount of the Building Permit Application fee in accordance with Schedule B of these Development and Building Regulations.
  • Payment of all outstanding fees is required prior to Building Permit issuance.

Trades Permits

Trade Permits must be obtained for all work regulated by the BC Building Code, UBC Development and Building Regulations and other policies. See Forms and Reference Materials page for all trade permit forms. 

Plumbing permits and fees are required for all UBC Vancouver projects that will include some type of fixture (e.g. roof drain, floor drain, hot water tank, commercial dishwasher, etc.). Sprinkler Permits are required for all UBC Vancouver projects. Depending on the project, your application may need to include sprinkler plans.

Plumbing/Fire Sprinkler Permit Application Form

Fire hydrant permits are mandatory for UBC to meet the requirements of several codes and regulations, the most critical being Section 6.6.4 of the British Columbia Fire Code. For UBC to meet the requirements of several important codes and regulations (e.g. BC Fire Code), a Hydrant Permit is required for temporary use of fire hydrants. Additional fees may apply. 

Fire Hydrant Connection Application Form 

Electrical, gas and elevator permits are issued by Technical Safety BC. 

Visit the Forms and Reference Materials page for all related application forms and reference materials. Questions? Contact us at permits.inspections@ubc.ca.