South Campus Greenway

The proposal is for an approximately 700m path that will be integrated within the existing treed area between UBC Farm and the Wesbrook Place Neighbourhood.

DP17024

Wesbrook Place Lots, 9, 10 & 38

  • Original DP application and plans received August 2, 2017
  • South Campus Greenway Design Principles Workshop was held on April 25, 2018 between 5:30-7:00 PM at the Wesbrook Community Centre.
  • Updated DP application and plans incorporting draft principles from the workshop received on May 16, 2019
  • Development Review Committee presentation to be held on May 23, 2019.
  • Public Consultation - Open House was held on May 28, 2019 between 4:30-6:30 PM at the Wesbrook Welcome Centre, 3378 Wesbrook Mall.
    • Public Comment Period May 16 - June 4, 2019
  • DP Board Resubmission received July 10, 2019.  
  • Development Permit Board presentation to be held at the Wesbrook Community Centre, 3335 Webber Lane, on July 17, 2019 starting at 5:00PM

 

 

 

Description

An updated Development Permit application was received on May 16, 2019 for a proposed greenway on the western edge of Wesbrook Place between Nobel Park and West 16th Avenue.  The path will be integrated within the existing treed area between UBC Farm and the Wesbrook Place Neighbourhood.

The 2019 resubmission incorporates the draft principles for the South Campus Greenway generated from a workshop last year along with modifications for the proposed plans.

A DP resubmission incorporating feedback from the May 28th Public Open House and subsequent consultation with the Farm is expected July 10, 2019.

 

Proponents

  • UBC Properties Trust

Manager, Development Services
(604) 822-1586