Updated: December 16, 2019
The proposal is for a new UBC Baseball Training Facility.
Development Permit
DP 14025
Location
Within the Thunderbird Park Precinct between Rashpal Dhillon Track & Field Oval and the Baseball Field north of West 16th Avenue.
Description
The new UBC Baseball Training Facility (1200 m2) will accommodate UBC T-Birds players, as well as baseball camps; softball leagues, the McKaig Performance Institute; and players from the lower mainland.
Proponents
- UBC Properties Trust
- Michael Green Architecture Inc.
Contact
Manager, Development Services
(604) 822-1586
Timeline
August 2014
Development permit and application plans submitted
August 2014
Development permit and application plans submitted
Development permit and application plans received August 21, 2014
September 2014
Public Open House
September 2014
Public Open House
Public Consultation - Open House held on September 03, 2014
February 2015
Development Permit Issued
February 2015
Development Permit Issued
Development Permit Issued February 6, 2015
March 2015
Construction
March 2015
Construction
Construction starts March 2015
September 2015
Provisional Occupancy
September 2015
Provisional Occupancy
Provisional Occupancy - September 2015