Updated: January 6, 2021
Development Permit
DP20037
Location
The northwest corner of Wesbrook Mall and University Boulevard
Proponents
UBC Properties Trust
Attachments
Presentation video: Aaron Knorr from Perkins & Will provides an overview of the proposed Gateway Building.
Contact
Manager, Development Services
(604) 822-1586
Timeline
December 23, 2020
Development Permit Application
A development permit application is received on December 23, 2020
January 24, 2021
Advisory Urban Design Panel
The application is reviewed by the Advisory Urban Design Panel on January 24, 2021
January 21, 2021
Development Review Committee
The application is reviewed by the UBC Development Review Committee on January 21, 2020
February 4, 2021
Virtual Public Open House Meetings
Two virtual public open house meetings were held on February 4, 2021 from 11:30 am to 1:00 pm and from 4:00 to 5:30 pm. Registrants were invited for a brief presentation by the project architect followed by a question and answer period with the applicant team and UBC Campus and Community Planning staff.
February 12, 2021
End of Public Comment Period
The online public comment period for this project closed on February 12, 2021.
October 19, 2021
Development Permit Issuance
A development permit issuance was issued for this project on October 19, 2021.