South Campus Greenway

Updated: December 10, 2019
Image
UBCmap greenway project banner
The proposal is for an approximately 700m path that will be integrated within the existing treed area between UBC Farm and the Wesbrook Place Neighbourhood.

Development Permit

DP17024

Location

Wesbrook Place Lots, 9, 10 & 38

Description

An updated Development Permit application was received on May 16, 2019 for a proposed greenway on the western edge of Wesbrook Place between Nobel Park and West 16th Avenue. The path will be integrated within the existing treed area between UBC Farm and the Wesbrook Place Neighbourhood.

The 2019 resubmission incorporates the draft principles for the South Campus Greenway generated from a workshop last year along with modifications for the proposed plans.

A DP resubmission incorporating feedback from the May 28th Public Open House and subsequent consultation with the Farm is expected July 10, 2019.

Proponents

  • UBC Properties Trust

Contact

Karen Russell

Manager, Development Services
(604) 822-1586

Timeline

August 2017
Original Development application and plans submitted
August 2017

Original Development application and plans submitted

Original Development application and plans received August 2, 2017

April 2018
Design Principles Workshop
April 2018

Design Principles Workshop

South Campus Greenway Design Principles Workshop was held on April 25, 2018 between 5:30 p.m. - 7:00 p.m. at the Wesbrook Community Centre

May 2019
Updated Development Permit application and plans submitted
May 2019

Updated Development Permit application and plans submitted

Updated Development Permit application and plans incorporating draft principles from the workshop received on May 16, 2019

May 2019
Development Review
May 2019

Development Review

Development Review Committee presentation to be held on May 23, 2019

May 2019
Public Open House
May 2019

Public Open House

Public Open House was held on May 28, 2019 between 4:30 p.m. - 6:30 p.m. at the Wesbrook Welcome Centre, 3378 Wesbrook Mall

May/June 2019
Public Comment Period
May/June 2019

Public Comment Period

Public Comment Period May 16 - June 4, 2019

July 2019
Development Permit Board
July 2019

Development Permit Board

Development Permit Board Resubmission received July 10, 2019

July 2019
Development Permit Board presentation
July 2019

Development Permit Board presentation

Development Permit Board presentation to be held at the Wesbrook Community Centre, 3335 Webber Lane, on July 17, 2019 starting at 5:00 p.m.