Digital Design Studio Addition

Updated: August 25, 2023
Image
DP23010 Banner
A development permit application has been received for an addition to the Chemical and Biological Engineering (CHBE) building. The proposal includes a two-storey, 950 sq. m addition within CHBE's service yard. The addition will connect to the existing interior atrium and includes a shop fabrication space on the lower level and class/lab studios, assembly, and conference rooms on the upper addition level.

Development Permit

DP 23010

Location

To the northwest, behind the existing Chemical and Biological Engineering Building at 2360 East Mall

Proponents

UBC Project Services

Documents

Contact

Karen Russell

Manager, Development Services
(604) 822-1586

Project Timeline

March 31, 2023
Application received
March 31, 2023

Application received

A development permit application is received by Campus and Community Planning

April 13, 2023
Advisory Panel
April 13, 2023

Advisory Panel

Advisory Urban Design Panel application presentation to occur on April 13, 2023

April 19, 2023
Public Open House
April 19, 2023

Public Open House

An Open House is planned for Wednesday, April 19, 2023, 11:30 AM - 1:30 PM in the foyer of the Fred Kaiser Building.

April 20, 2023
Development Review Committee
April 20, 2023

Development Review Committee

The project is presented to the UBC Development Review Committee for staff review and comment.

May 2023
Board of Governors Meeting
May 2023

Board of Governors Meeting

Board of Governors Meeting to occur in early May

August 25, 2023
Development Permit Issuance
August 25, 2023

Development Permit Issuance

A Development Permit was issued in August 25, 2023

March 2024
Construction Commences
March 2024

Construction Commences

Construction is anticipated to begin in March 2024