Development Permit

DP18028

Location

Lot 4 - Wesbrook Place

Description

A new 11,332m2 rental residential project with 135 units for faculty and staff comprising two linked 6-storey buildings.

Proponents

  • UBC Properties Trust

Contact

Karen Russell

Manager, Development Services
(604) 822-1586

Timeline

May 2018
Pre-Application Panel
May 2018

Pre-Application Panel

Pre-Application Advisory Urban Design Panel presentation was held on May 3, 2018

June 2018
Development Permit application and plans submitted
June 2018

Development Permit application and plans submitted

Development Permit application and plans submitted on June 29, 2018

July 2018
Advisory Panel
July 2018

Advisory Panel

Advisory Urban Design Panel presentation to be held on July 5, 2018

July 2018
Development Review
July 2018

Development Review

Development Review Committee presentation scheduled for July 12, 2018

July 2018
Public Open House
July 2018

Public Open House

Public Open House scheduled for Tuesday, July 17, 2018, between 4:30 p.m. - 6:00 p.m., at the Wesbrook Welcome Centre

June/July 2018
Public Comment Period
June/July 2018

Public Comment Period

Public Comment Period June 29 - July 24, 2018

July 2018
Development Permit Resubmission 1
July 2018

Development Permit Resubmission 1

Development Permit Resubmission 1 submitted July 30, 2018

August 2018
Development Permit Board
August 2018

Development Permit Board

Development Permit Board presentation was held on August 8, 2018 between 5:00 p.m. - 6:00 p.m. at the Wesbrook Community Centre

September 2018
Development Permit Resubmission 2
September 2018

Development Permit Resubmission 2

Development Permit Resubmission 2 submitted September 14, 2018

October 2018
Development Permit Issued
October 2018

Development Permit Issued

Development Permit Issued October 3, 2018

January 2019
Foundation & Structural to Grade
January 2019

Foundation & Structural to Grade

Foundation & Structural to Grade issued January 1, 2019

April 2019
Full Building Permit Issued
April 2019

Full Building Permit Issued

Full Building Permit Issued April 29, 2019