The proposal is for a market residential project on Lots 7 &8 in Wesbrook Place.

Development Permit

DP17016

Location

Wesbrook Place Lots 7 & 8

Description

"The Residences at Nobel Park", a new 29,280 m2 market residential project comprising 267 units within a 14-storey highrise, 5-storey mid-rise and 2/3-storey townhomes.

Proponents

  • Polygon
  • Frankl Architecture 

Contact

Karen Russell

Manager, Development Services
(604) 822-1586

Timeline

April 2017
Pre-Application Panel
April 2017

Pre-Application Panel

Pre-Application Advisory Urban Design Panel presentation was held on April 6, 2017

June 2017
Development Permit application and plans submitted
June 2017

Development Permit application and plans submitted

Development Permit application and plans received June 1, 2017

June 2017
Advisory Panel
June 2017

Advisory Panel

Advisory Urban Design Panel presentation was held on June 1, 2017

June 2017
Development Review
June 2017

Development Review

Development Review Committee presentation to be held on  June 8, 2017

June 2017
Public Open House
June 2017

Public Open House

Public Open House scheduled for June 20, 2017, between 5:00 p.m. - 6:30 p.m., at the Wesbrook Welcome Centre, 3378 Wesbrook Mall

June 2017
Public Comment Period
June 2017

Public Comment Period

Online Comment Period June 5 - June 27, 2017

July 2017
Development Permit Board
July 2017

Development Permit Board

Development Permit Board presentation held on July 26, 2017, between 5:00 p.m. - 7:00 p.m. at the Wesbrook Community Centre, 3335 Webber Lane

August 2017
Development Permit
August 2017

Development Permit

Development Permit Issued August 31, 2017

January 2018
Excavation and Shoring Permit Issued
January 2018

Excavation and Shoring Permit Issued

Excavation and Shoring Permit Issued January 8, 2018

April 2018
Foundation & Structural to Grade Permit Issued
April 2018

Foundation & Structural to Grade Permit Issued

Foundation & Structural to Grade Permit Issued April 20, 2018

August 2018
Development Permit Amendment 1 Issued
August 2018

Development Permit Amendment 1 Issued

Development Permit Amendment 1 Issued August 1, 2018

October 2018
Full Building Permit Issued
October 2018

Full Building Permit Issued

Full Building Permit Issued October 16, 2018