The proposal is for a new 10,500m2 neighbourhood park on the former BC Research Site, south of Gray Avenue and East of Wesbrook Mall
Development Permit
DP17007
Location
Former BC Research Site, South East Quadrant of Wesbrook Place
Contact
Manager, Development Services
(604) 822-1586
Timeline
March 2017
Development Permit and application plans submitted
March 2017
Development Permit and application plans submitted
Development Permit and application plans received March 30, 2017
April 2017
Advisory Panel
April 2017
Advisory Panel
Advisory Urban Design Panel Presentation held on April 6, 2017
September 2017
Development Review
September 2017
Development Review
Development Review Committee presentation to be held on September 14, 2017
July 2017
Public Open House
July 2017
Public Open House
Public Open House was held on July 25, 2017 between 5:00 p.m. - 7:00 p.m. at the Wesbrook Welcome Centre
July/August 2017
Public Comment Period
July/August 2017
Public Comment Period
Public Comment Period July 10 - August 1, 2017
October 2017
Development Permit Board
October 2017
Development Permit Board
Development Permit Board presentation was held at the Wesbrook Community Centre on October 11, 2017
February 2018
Development Permit Issued
February 2018
Development Permit Issued
Development Permit Issued February 21, 2018
April 2018
Streets and Landscape Permit Issued
April 2018
Streets and Landscape Permit Issued
Streets and Landscape Permit Issued April 23, 2018
Attachments
File | Category |
DP17007 10-03-2017 Final Permit Set | Plans |
DP17007 09-08-2017 Landscape Resubmission | Reference Material |
DP17007 Landscape Drawing Set | Reference Material |
DP17007 Public Open House Display Boards | Reference Material |